Violation Detail
Standard Cited: 19100119 J04 I Process safety management of highly hazardous chemicals.
Inspection Nr: 1228975.015
Citation: 01006B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/27/2017
Nr Instances: 2
Nr Exposed: 5
Abatement Date: 02/03/2020
Gravity: 5
Report ID: 0134000
Contest Date: 11/20/2017
Final Order: 03/09/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/09/2018 | $0.00 | 02/03/2020 | Serious | |
Penalty | C: Contested | 12/04/2017 | $0.00 | 11/27/2017 | Serious | |
Penalty | Z: Issued | 10/27/2017 | $0.00 | 11/27/2017 | Serious |
Text For Citation: 01 Item/Group: 006B Hazard:
29 CFR 1910.119(j)(4)(i): Inspections and tests were not performed on process equipment: (a) Location - 638 Summer Street, Lynn, MA: On or about 5/1/2017, Reactor U-4 has not been inspected. (b) Location - 638 Summer Street, Lynn, MA: On or about 5/1/2017, process piping associated with the manufacture of Product has not been hydrostatically tested.