Violation Detail
Standard Cited: 19100303 G01 I C General.
Inspection Nr: 1208998.015
Citation: 01006B
Citation Type: Serious
Abatement Date: 06/28/2017 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/11/2017
Nr Instances: 3
Nr Exposed: 2
Related Event Code (REC): C
Gravity: 5
Report ID: 0112000
Contest Date:
Final Order: 06/01/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/01/2017 | $0.00 | 06/28/2017 | Serious | |
Penalty | Z: Issued | 05/11/2017 | $0.00 | 06/28/2017 | Serious |
Text For Citation: 01 Item/Group: 006B Hazard:
29 CFR 1910.303(g)(1)(i)(C): For electric equipment operating at 600 volts, nominal, or less to ground, and likely to require examination, adjustment, servicing, or maintenance while energized, the width of work space was not clear and did not extend from the grade, floor, or platform to the height required by paragraph (g)(1)(vi) of 29 CFR 1910.303: A. 11 Cody Street, Machine Shop: On, or about, February 6, 2017, a Jefferson and an Eaton transformer had been installed on the floor in front of two disconnect switches and a small circuit breaker box. B. 11 Cody Street, Electrical Panels near Spray Line: On, or about, February 6, 2017, a Federal Pacific transformer was installed on the floor in front of two circuit breaker panels.