Violation Detail
Standard Cited: 19100217 E01 I Mechanical power presses.
Inspection Nr: 1820405.015
Citation: 01006A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,674.00
Current Penalty: $3,000.00
Issuance Date: 08/11/2025
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 09/29/2025
Gravity: 1
Report ID: 0521700
Contest Date:
Final Order: 08/28/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/28/2025 | $3,000.00 | 09/29/2025 | Serious | |
Penalty | Z: Issued | 08/11/2025 | $5,674.00 | 08/28/2025 | Serious |
Text For Citation: 01 Item/Group: 006A Hazard:
29 CFR 1910.217(e)(1)(i): A program of periodic and regular inspections of mechanical power press(es) was not established and followed to ensure that all parts, auxiliary equipment and safeguards were in a safe operating condition and adjustment:(a) a) On or about April 24, 2025, in the power press department, the employer failed to ensure that periodic and regular inspections of each power press, such as but not limited to the Bliss C60 100 Ton Mechanical Power Press Machine, were conducted to make sure all components of the machine were working properly. The employer also failed to ensure that employees perform and complete necessary maintenance or repair before operating the presses, along with ensuring that certification records are being maintained.