Violation Detail
Standard Cited: 19260752 D Site layout, site-specific erection plan and construction sequence.
Inspection Nr: 1475116.015
Citation: 01006A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,446.00
Current Penalty: $6,250.00
Issuance Date: 11/10/2020
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 12/30/2020
Gravity: 10
Report ID: 0112000
Contest Date:
Final Order: 12/09/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/09/2020 | $6,250.00 | 12/30/2020 | Serious | |
Penalty | Z: Issued | 11/10/2020 | $9,446.00 | 12/30/2020 | Serious |
Text For Citation: 01 Item/Group: 006A Hazard:
29 CFR 1926.752(d): Pre-planning of overhead hoisting operations. All hoisting operations in steel erection were not pre-planned to ensure that the requirements of 1926.753(d) are met. On or about 05/12/2020 employees at the PDQ, INC. steel erection jobsite were exposed to overhead hazards during hoisting operations. Employer did not conduct pre-planning prior to conducting overhead hoisting operations.