Violation Detail
Standard Cited: 19100265 C04 IV Sawmills.
Inspection Nr: 1443494.015
Citation: 01006A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,398.00
Current Penalty: $2,159.00
Issuance Date: 03/16/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 07/31/2020
Gravity: 5
Report ID: 0521100
Contest Date:
Final Order: 04/09/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | P: Petition to Mod Abatement | 05/06/2020 | $2,159.00 | 07/31/2020 | Serious | |
| Penalty | I: Informal Settlement | 04/09/2020 | $2,159.00 | 05/08/2020 | Serious | |
| Penalty | Z: Issued | 03/16/2020 | $5,398.00 | 04/20/2020 | Serious |
Text For Citation: 01 Item/Group: 006A Hazard:
29 CFR 1910.265(c)(4)(iv): Elevated walks. All elevated walks, runways, or platforms, if 4 feet or more from the floor level, shall be provided with a standard railing except on loading or unloading sides of platforms. If height exceeds 6 feet, a standard toe board also shall be provided to prevent material from rolling or falling off. On November 7, 2019 employees exposed to a four feet and greater fall hazard from a section of the De-Barker machine platform that did not have a guardrail.