Violation Detail
Standard Cited: 19260062 D01 I Lead
Inspection Nr: 1288638.015
Citation: 01006A
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $9,239.00
Current Penalty: $9,239.00
Issuance Date: 07/17/2018
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 08/10/2018
Gravity: 5
Report ID: 0317000
Contest Date: 07/27/2018
Final Order: 02/19/2019
Related Event Code (REC): R
Emphasis:
Substance: BWPB
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 02/19/2019 | $9,239.00 | 08/10/2018 | Serious | |
Penalty | C: Contested | 09/11/2018 | $9,239.00 | 08/10/2018 | Serious | |
Penalty | Z: Issued | 07/17/2018 | $9,239.00 | 08/10/2018 | Serious |
Text For Citation: 01 Item/Group: 006A Hazard:
29 CFR 1926.62(d)(1)(i): Each employer who had a workplace or operation covered by 29 CFR 1926.62 did not initially determine if any employee was exposed to lead at or above the action level of 30 micrograms per cubic meter of air (30 ug/m3) calculated as an 8-hour time-weighted average (TWA): (a) River Station Demolition Project, Downingtown, PA - On or about 1/17/18, the employer did not conduct an initial exposure assessment of employees performing torch burning of steel where lead was present, exposing employees to chemical hazards.