Violation Detail
Standard Cited: 19100303 G01 I General.
Inspection Nr: 1151844.015
Citation: 01006A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,471.00
Current Penalty: $10,000.00
Issuance Date: 10/31/2016
Nr Instances: 3
Nr Exposed: 1400
Abatement Date: 06/01/2017
Gravity: 10
Report ID: 0522000
Contest Date: 11/16/2016
Final Order: 05/10/2017
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/10/2017 | $10,000.00 | 06/01/2017 | Serious | |
Penalty | C: Contested | 11/16/2016 | $12,471.00 | 11/28/2016 | Serious | |
Penalty | Z: Issued | 10/31/2016 | $12,471.00 | 11/28/2016 | Serious |
Text For Citation: 01 Item/Group: 006A Hazard:
29 CFR 1910.303(g)(1)(i): Working space for equipment likely to require examination, adjustment, servicing, or maintenance while energized shall comply with the following dimensions, except as required or permitted elsewhere in this subpart: The depth of the working space in the direction of access to live parts may not be less than indicated in Table S-1: (a) The distance between the front panel cover on the 600 VAC GE Heavy Duty Safety Switch by Post AA 35, and the metal fencing in front of it, did not comply with Table S-1, in that the distance between the front panel cover and the metal fencing was only 24 inches. (b) The distance between the front panel cover on the 600 VAC GE Heavy Duty Safety Switch by Post N 36, and the metal storage racks in front of it, did not comply with Table S-1, in that the distance between the front panel cover and the metal storage racks was only 27-1/2 inches.