Violation Detail
Standard Cited: 19261101 G05 I B 1 Asbestos
Inspection Nr: 1141444.015
Citation: 01006A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,988.00
Current Penalty: $2,400.00
Issuance Date: 10/18/2016
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 11/16/2016
Gravity: 10
Report ID: 0523300
Contest Date: 11/07/2016
Final Order: 07/30/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/30/2018 | $2,400.00 | 11/16/2016 | Serious | |
Penalty | C: Contested | 11/09/2016 | $4,988.00 | 11/16/2016 | Serious | |
Penalty | Z: Issued | 10/18/2016 | $4,988.00 | 11/16/2016 | Serious |
Text For Citation: 01 Item/Group: 006A Hazard:
29 CFR 1926.1101(g)(5)(i)(B)(1): Before the beginning of each shift the negative pressure enclosure was not inspected for breaches and smoke-tested for leaks: On or about April 20, 2016 the asbestos containment was not inspected for breaches and smoke tested for leaks.