Violation Detail
Standard Cited: 5A0001 OSH Act General Duty Paragraph
Inspection Nr: 309429009
Citation: 01006
Citation Type: Serious
Abatement Status: X
Initial Penalty: $1,700.00
Current Penalty: $1,275.00
Issuance Date: 05/26/2006
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 06/02/2006
Gravity: 02
Report ID: 0418800
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/13/2006 | $1,275.00 | 06/02/2006 | Serious | |
| Penalty | Z: Issued | 05/26/2006 | $1,700.00 | 06/02/2006 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard: UNAPOPPROC
29 CFR 1910.179(m)(1): Thorough monthly inspections of rope conditions, with written, dated and signed reports, were not performed on the running ropes: On or 01/27/06, on the feeder floor between the # 2 and # 4 boiler, the wire rope on an overhead crane was not inspected on a monthly basis for damage or defects. PLEASE NOTE: CERTIFICATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Translate