Standard Cited: 19100303 B07 IV General.
Inspection Nr: 1455498.015
Citation: 01006
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $9,543.00
Current Penalty: $3,000.00
Issuance Date: 05/26/2020
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 5
Report ID: 0134000
Contest Date:
Final Order: 06/23/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/23/2020 | $3,000.00 | Serious | ||
Penalty | Z: Issued | 05/26/2020 | $9,543.00 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1910.303(b)(7)(iv): There were damaged parts adversely affecting safe operation or mechanical strength of equipment, such that parts were broken, bent, cut, or deteriorated by corrosion, chemical action, or overheating: Location: CIP Skid Area On or about 01/09/2020, employees were exposed to electric shock and fire hazards from the on/off switch missing on the 480-volt electrical panel (EEP1) exposing the internal live wires.