Violation Detail
Standard Cited: 19100119 J04 I Process safety management of highly hazardous chemicals.
Inspection Nr: 1331529.015
Citation: 01006
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,934.00
Current Penalty: $7,760.40
Issuance Date: 11/29/2018
Nr Instances: 18
Nr Exposed: 6
Abatement Date: 06/30/2019
Gravity: 10
Report ID: 0627510
Contest Date:
Final Order: 01/21/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/21/2019 | $7,760.40 | 06/30/2019 | Serious | |
Penalty | Z: Issued | 11/29/2018 | $12,934.00 | 12/18/2018 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1910.119(j)(4)(i): The employer did not perform inspection and tests on process equipment. On or about July 18, 2018, the employer does not perform inspection and tests on process equipment in accordance with ANSI/IIAR B110 when it failed to replace pressure relief valves at interval that exceeded the five years, this exposed employees to explosion hazard a. VS 106 Intercooler PSV 1601 b. VS 106 Intercooler PSV 1602 c. VS 122 VS-122 Oil Separator for BS 102 PSV 1316 d. VS 117 VS-117 Oil Separator on CP 102 PSV 1610 e. VS 118 VS-118 Oil Separator on CP 103 PSV 1649 f. VS 120 VS-120 Oil Separator on CP 104 PSV 1650 g. VS 119 Oil Separator on CP 105 PSV 1318 h. VS 119 Oil Separator on CP 105 PSV 1319 i. VS 127 Surge Drum on GC 101 PSV 1636 j. VS 127 Surge Drum on GC 101 PSV 1637 k. VS 135 Surge Drum on GC 102 PSV 1883 l. VS 135 Surge Drum on GC 102 PSV 1884 m. GC 102 Plates PSV 1885 n. GC 102 Plates PSV 1886 o. VS 136 Oil Pot for Surge Drum VS-135. PSV 1887 p. VS 101 High Pressure Receiver PSV 1638 q. VS 101 High Pressure Receiver PSV 1639 r. CP 101 Screw Compressor