Violation Detail
Standard Cited: 19100176 A Handling materials - general.
Inspection Nr: 1330241.015
Citation: 01006
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,989.00
Current Penalty: $2,993.40
Issuance Date: 10/09/2018
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 11/02/2018
Gravity: 1
Report ID: 0418100
Contest Date:
Final Order: 10/22/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/22/2018 | $2,993.40 | 11/02/2018 | Serious | |
Penalty | Z: Issued | 10/09/2018 | $4,989.00 | 11/02/2018 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1910.176(a): Where mechanical handling equipment was used, sufficient safe clearances were not allowed for aisles, at loading docks, through doorways or wherever turns or passage had to be made. Permanent aisles or passageways were not appropriately marked. On 7/17/18, in the Assembly Plant warehouse area, employees were exposed to struck by hazards in the area where mechanical equipment was used/operated and permanent aisles/passageways were not marked.