Violation Detail
Standard Cited: 19260451 H02 II General requirements.
Inspection Nr: 1244918.015
Citation: 01006
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,889.00
Current Penalty: $2,933.00
Issuance Date: 12/07/2017
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 01/04/2018
Gravity: 1
Report ID: 0316300
Contest Date:
Final Order: 12/20/2017
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/20/2017 | $2,933.00 | 01/04/2018 | Serious | |
| Penalty | Z: Issued | 12/07/2017 | $4,889.00 | 01/04/2018 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1926.451(h)(2)(ii): A toeboard was not erected along the edge of platforms more than 10 feet (3.1 m) above lower levels for a distance sufficient to protect employees below: (a) Date of Violation: On or about 07-06-2017 and times prior thereto, located at NAS Oceana - Dam Neck Annex 352 Bullpup Street. Virginia Beach, VA 23461, Condition: Employee(s) were exposed to struck-by hazards from a welded tubular steel scaffolding system that did not contain toe-boards at the inward areas where employees pass underneath. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employee(s) and their representatives were informed of this abatement.
Translate