Violation Detail
Standard Cited: 19100119 N Process safety management of highly hazardous chemicals.
Inspection Nr: 1176890.015
Citation: 01006
Citation Type: Other
Abatement Date: 03/27/2017 2
Initial Penalty: $9,959.00
Current Penalty: $4,979.50
Issuance Date: 03/10/2017
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC):
Gravity:
Report ID: 0627510
Contest Date: 04/18/2017
Final Order: 11/03/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 11/03/2017 | $4,979.50 | 03/27/2017 | Other | |
Penalty | C: Contested | 04/18/2017 | $9,959.00 | 03/27/2017 | Serious | |
Penalty | Z: Issued | 03/10/2017 | $9,959.00 | 03/27/2017 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1910.119(n): The employer did not establish and implement an emergency plan for the entire plant in accordance with the provisions of 29 CFR 1910.38 Throughout the facility, employer did not: a) did not ensure that employees recognized the difference between small and large releases for highly hazardous chemicals. b) did not review the emergency evacuation procedures with visitors and non-employees.