Standard Cited: 19260416 A01 General requirements.
Inspection Nr: 1169831.015
Citation: 01006
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,338.00
Current Penalty: $3,802.80
Issuance Date: 01/31/2017
Nr Instances: 2
Nr Exposed: 6
Abatement Date: 02/23/2017
Gravity: 5
Report ID: 0627700
Contest Date:
Final Order: 03/22/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/22/2017 | $3,802.80 | 02/23/2017 | Serious | |
Penalty | Z: Issued | 01/31/2017 | $6,338.00 | 02/23/2017 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: a. On or about August 4, 2016, by turbine 3 at the downstream wall, the raceway that held energized electrical cables lacked a cover and the energized electrical cables were not guarded to prevent employee contact which exposes employees to electrical hazards. b. On or about August 4, 2016, by turbine 1 at the downstream wall, the raceway that held energized electrical cables lacked a cover and the energized electrical cables were not guarded to prevent employee contact which exposes employees to electrical hazards.