Violation Detail
Standard Cited: 19261415 B
Inspection Nr: 1129879.015
Citation: 01006
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $2,520.00
Current Penalty: $1,000.00
Issuance Date: 07/29/2016
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 08/15/2016
Gravity:
Report ID: 0627100
Contest Date: 08/15/2016
Final Order: 02/13/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 02/13/2017 | $1,000.00 | 08/15/2016 | Other | |
Penalty | C: Contested | 08/15/2016 | $2,520.00 | 08/15/2016 | Serious | |
Penalty | Z: Issued | 07/29/2016 | $2,520.00 | 08/15/2016 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1926.1415(b): The employer permitted operations to begin or continue before all of the devices listed in this section were in proper working order. The employer permitted operation of the Manitowoc Boom Truck - Manitex Crane Model M2277 to begin before the horn was in working order.