Violation Detail
Standard Cited: 19150055 E04 Gas welding and cutting.
Inspection Nr: 1099323.015
Citation: 01006
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,900.00
Current Penalty: $2,500.00
Issuance Date: 03/01/2016
Nr Instances: 2
Nr Exposed: 50
Abatement Date: 03/11/2016
Gravity: 10
Report ID: 0523100
Contest Date:
Final Order: 03/29/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/29/2016 | $2,500.00 | 03/11/2016 | Serious | |
Penalty | Z: Issued | 03/01/2016 | $4,900.00 | 03/11/2016 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1915.55(e)(4): Manifold and header hose connections were not capped when not in use. (a) On or about October 23, 2015, under the AMTO tug mezzanine, the employer failed to ensure fuel and gas manifold and header hose connections were capped when not in use. Employees were exposed to explosions. (b) On or about October 23, 2015, on top of the mezzanine for the AMTO tug, the employer failed to ensure fuel and gas manifold and header hose connections were capped when not in use. Employees were exposed to explosions.