Violation Detail
Standard Cited: 19100303 B08 III General.
Inspection Nr: 1084449.015
Citation: 01006
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $4,200.00
Current Penalty: $2,730.00
Issuance Date: 12/18/2015
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 01/15/2016
Gravity:
Report ID: 0317500
Contest Date:
Final Order: 01/13/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/13/2016 | $2,730.00 | 01/15/2016 | Other | |
Penalty | Z: Issued | 12/18/2015 | $4,200.00 | 01/15/2016 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1910.303(b)(8)(iii): Electric equipment provided with ventilating openings were not installed so that walls or other obstructions did not prevent the free circulation of air through the equipment: a) K Plant, electrical panels behind the hydraulic presses, 6th and Center Streets, Tarentum, Pennsylvania 15084: Observed on or about July 28, 2015, both air vents on the front of the motor control center for the #3 hydraulic press (LAEIS model number HVAKP 2000) were blocked with cardboard. The blocked vents could result in the overheating of energized conductors (480 volt, 3 phase) housed inside the motor control center. The cabinet was labeled as a HRC Level 0 arc flash and shock hazard. Press operators, electricians, and laborers working in the area of the #3 press motor control center were exposed to the arc flash, electric shock, and electrocution hazards.