Violation Detail
Standard Cited: 19100305 G01 IV D Wiring methods, components, and equipment for general use.
Inspection Nr: 1377874.015
Citation: 01005D
Citation Type: Serious
Abatement Date: 04/29/2019 2
Initial Penalty: $5,304.00
Current Penalty: $0.00
Issuance Date: 04/03/2019
Nr Instances: 1
Nr Exposed: 11
Related Event Code (REC):
Gravity: 10
Report ID: 0626300
Contest Date:
Final Order: 04/23/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/23/2019 | $0.00 | 04/29/2019 | Serious | |
Penalty | Z: Issued | 04/03/2019 | $5,304.00 | 04/29/2019 | Serious |
Text For Citation: 01 Item/Group: 005D Hazard:
29 CFR 1910.305(g)(1)(iv)(D): Flexible cords and cables were attached to building surfaces: (a) Employees at the site were exposed to electrical shock hazards when a flexible cord was attached to the rafters of the structure.