Violation Detail
Standard Cited: 19260251 C04 IV Rigging equipment for material handling.
Inspection Nr: 1314167.015
Citation: 01005C
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/12/2018
Nr Instances: 1
Nr Exposed: 10
Abatement Date: 07/18/2018
Gravity:
Report ID: 0134000
Contest Date: 11/22/2018
Final Order: 11/22/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 11/22/2019 | $0.00 | 07/18/2018 | Other | |
Penalty | C: Contested | 07/27/2018 | $0.00 | 07/18/2018 | Serious | |
Penalty | Z: Issued | 07/12/2018 | $0.00 | 07/18/2018 | Serious |
Text For Citation: 01 Item/Group: 005C Hazard:
29 CFR 1926.251(c)(4)(iv): Wire rope(s) were used in which the total number(s) of visible broken wires exceeded 10 percent of the total number of wires and in which the rope(s) showed other signs of defect(s): Hotel 28th Level, Middle On or about April 27, 2018, the wire rope sling, attached to the rear of the DBL scale pan had 1.5 of five stands (>25%) cut/broken.