Violation Detail
Standard Cited: 19100217 E01 II A Mechanical power presses.
Inspection Nr: 1285386.015
Citation: 01005B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/14/2018
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 06/20/2018
Gravity: 10
Report ID: 0317300
Contest Date: 07/06/2018
Final Order: 05/16/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/16/2019 | $0.00 | 06/20/2018 | Serious | |
Penalty | C: Contested | 07/09/2018 | $0.00 | 06/20/2018 | Serious | |
Penalty | Z: Issued | 06/14/2018 | $0.00 | 06/20/2018 | Serious |
Text For Citation: 01 Item/Group: 005B Hazard:
29 CFR 1910.217(e)(1)(ii)(A): Inspections and tests of each press on a weekly basis were not being completed to determine the condition of the clutch/ brake mechanism, anti-repeat feature and single stroke mechanism. a) 7th and Washington St. New Castle, DE-On or about December 19, 2017, the employer failed to perform inspections and tests of each press on a weekly basis to determine the condition of the clutch/brake mechanism, anti-repeat feature and single stroke mechanist. Abatement Note: The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.