Violation Detail
Standard Cited: 19100119 J04 I Process safety management of highly hazardous chemicals.
Inspection Nr: 1277754.015
Citation: 01005B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,477.00
Current Penalty: $0.00
Issuance Date: 05/14/2018
Nr Instances: 17
Nr Exposed: 8
Abatement Date: 06/01/2018
Gravity: 10
Report ID: 0626600
Contest Date:
Final Order: 06/07/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/07/2018 | $0.00 | 06/01/2018 | Serious | |
Penalty | Z: Issued | 05/14/2018 | $10,477.00 | 06/01/2018 | Serious |
Text For Citation: 01 Item/Group: 005B Hazard:
29 CFR 1910.119(j)(4)(i): The employer did not perform inspection and tests on process equipment: On or about November 14, 2017, and at times prior thereto, the employer did not perform inspection and tests on process equipment to maintain its on-going mechanical integrity, in the chlorine process area, for equipment including but not limited to: a) ET201: Expansion Chamber b) ET202: Expansion chamber c) ET203: Expansion Chamber d) ET204: Expansion Chamber e) ET201: Pressure relief disk f) ET202: Pressure relief disk g) ET203: Pressure relief disk h) ET204: Pressure relief disk i) Pipeline 1 CL-201-CS1 to 2-CL-201-CS1 injection into Powell Unit j) Pipeline 1 CL-219-GCS1 k) Rail Car Hoses H219 & H220 l) I-203 (Interlock) m) I-206 (Interlock) n) I-208 (Interlock) o) AutoMax Valve p) Main PLC q) Unit Emergency shutdowns