Violation Detail
Standard Cited: 19260351 B03 Arc welding and cutting.
Inspection Nr: 1611035.015
Citation: 01005A
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $7,252.00
Current Penalty: $3,550.00
Issuance Date: 11/07/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 5
Report ID: 0521700
Contest Date:
Final Order: 11/30/2022
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/30/2022 | $3,550.00 | Serious | ||
Penalty | Z: Issued | 11/07/2022 | $7,252.00 | Serious |
Text For Citation: 01 Item/Group: 005A Hazard:
29 CFR 1926.351(b)(3):When it became necessary to connect or splice lengths of cable one to another, substantial insulated connectors of a capacity at least equivalent to that of the cable were not used: a. On or about July 26, 2022, at the above addressed jobsite, a welding lead was spliced with duct tape, thereby exposing employees to the hazards associated with electrocution.