Standard Cited: 19100303 B01 II General.
Inspection Nr: 1450674.015
Citation: 01005A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,398.00
Current Penalty: $2,699.00
Issuance Date: 05/19/2020
Nr Instances: 1
Nr Exposed: 25
Abatement Date: 12/01/2021
Gravity: 5
Report ID: 0420600
Contest Date:
Final Order: 06/15/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/15/2020 | $2,699.00 | 12/01/2021 | Serious | |
Penalty | Z: Issued | 05/19/2020 | $5,398.00 | 06/22/2020 | Serious |
Text For Citation: 01 Item/Group: 005A Hazard:
29 CFR 1910.303(b)(1)(ii): Electrical equipment was not free from recognized hazards, based on the mechanical strength and durability, including, for parts designed to enclose and protect other equipment, the adequacy of the protection thus provided: a. On or about 12/12/2019, at the fabrication area, S-11 column, employees were exposed to electrical hazards, in that, a breaker panel with 14 breakers and a breaker panel with 7 breakers were not provided with a cover door, were corroded, and were subject to getting wet. The panel with 14 breakers was damaged and bent on the left side.