Violation Detail
Standard Cited: 19100303 B01 II General.
Inspection Nr: 1333866.015
Citation: 01005A
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $12,934.00
Current Penalty: $5,000.00
Issuance Date: 11/30/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 10
Report ID: 0627100
Contest Date:
Final Order: 01/15/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/15/2019 | $5,000.00 | Serious | ||
Penalty | Z: Issued | 11/30/2018 | $12,934.00 | Serious |
Text For Citation: 01 Item/Group: 005A Hazard:
29 CFR 1910.303(b)(1)(ii): Electrical equipment was not free from recognized hazards, based on the mechanical strength and durability, including, for parts designed to enclose and protect other equipment, the adequacy of the protection thus provided: On or about July 25, 2018 and times prior, the employer did not ensure that parts on the back of the control panel for Hall 6H tilt-mold machine designed to protect approximately 480V electricity was adequately enclosed. This condition exposed employees working on the machine to electric hazards.