Violation Detail

Standard Cited: 19100303 B02 General.

Inspection Nr: 1298176.015

Citation: 01005A

Citation Type: Serious

Abatement Status: Abatement Completed

Initial Penalty: $4,989.00

Current Penalty: $3,500.00

Issuance Date: 04/11/2018

Nr Instances: 2

Nr Exposed: 1

Abatement Date: 05/29/2018

Gravity: 1

Report ID: 0729300

Contest Date:

Final Order: 05/09/2018

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 05/09/2018 $3,500.00 05/29/2018 Serious  
Penalty Z: Issued 04/11/2018 $4,989.00 05/29/2018 Serious  

Text For Citation: 01 Item/Group: 005A Hazard:

29 CFR 1910.303(b)(2): Listed or labeled electrical equipment was not used or installed in accordance with instructions included in the listing or labeling: a. In the aluminum building, the electrical cabinet door to die cast machine #7-003, was open during operation of the machine. b. In the aluminum building, the electrical cabinet door to the die cast melting pot #7-004, was open during operation of the machine. Abatement documentation is required for this violation.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.