Violation Detail
Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
Inspection Nr: 1282328.015
Citation: 01005A
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $9,239.00
Current Penalty: $4,975.40
Issuance Date: 06/07/2018
Nr Instances: 3
Nr Exposed: 8
Abatement Date: 07/26/2018
Gravity:
Report ID: 0214200
Contest Date: 06/28/2018
Final Order: 01/18/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/18/2019 | $4,975.40 | 07/26/2018 | Other | |
Penalty | C: Contested | 07/13/2018 | $9,239.00 | 07/26/2018 | Serious | |
Penalty | Z: Issued | 06/07/2018 | $9,239.00 | 07/26/2018 | Serious |
Text For Citation: 01 Item/Group: 005A Hazard:
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going integrity of process equipment: b) Compressor room 35 - The employer failed to properly document its mechanical integrity procedure when it failed to perform electrical components of Class A inspections on compressors RB-1, RC-1, RC-2, RC-4 and RC-5 in 2017. Violation occurred on or about 12/11/17. c) Compressor room 35 The employer failed to properly document its mechanical integrity procedure when it failed to perform electrical components of Class B inspections on compressors RB-1 and RC-5 in 2017. Violation occurred on or about 12/11/17.