Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 1278776.015
Citation: 01005A
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $10,163.00
Current Penalty: $6,097.50
Issuance Date: 05/07/2018
Nr Instances: 5
Nr Exposed: 258
Abatement Date:
Gravity: 5
Report ID: 0213100
Contest Date: 06/05/2018
Final Order: 08/31/2018
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/31/2018 | $6,097.50 | Serious | ||
Penalty | C: Contested | 06/06/2018 | $10,163.00 | Serious | ||
Penalty | Z: Issued | 05/07/2018 | $10,163.00 | Serious |
Text For Citation: 01 Item/Group: 005A Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: a) Main Building Buildings 2, 3, and 4 - On December 1, 2017, and at times prior, the employer did not legibly mark each disconnecting means, and circuit breaker inside panel boxes, as to its purpose.