Violation Detail
Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1064409.015
Citation: 01005A
Citation Type: Serious
Abatement Date: 12/03/2015 2
Initial Penalty: $4,500.00
Current Penalty: $2,925.00
Issuance Date: 07/24/2015
Nr Instances: 5
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0729300
Contest Date:
Final Order: 08/21/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/21/2015 | $2,925.00 | 12/03/2015 | Serious | |
Penalty | Z: Issued | 07/24/2015 | $4,500.00 | 09/10/2015 | Serious |
Text For Citation: 01 Item/Group: 005A Hazard:
29 CFR 1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s): Inside of the Fabrication Shop, the 480 volt electrical, hydraulics, and gravity energy sources belonging to the following machines were not isolated by employee(s) prior to changing out the dies: a/ K.R. Wilson Hydraulic Press, m/n 3700V2-B, s/n 2051. b/ Bliss Mechanical Punch Press, m/n 5012, unknown s/n. c/ Willis-Bergo Radial Arm Drill, m/n FS1000, unknown s/n. Inside of the Machine Shop, the 480 volt electrcial energy sources belonging to the following machines were not isolated by employee(s) prior to changing out the bits. a/ W.B. Knight Milling Machine, m/n J, unknown s/n. b/ HAAS Vertical Machining Center, m/n BF2, m/n 2080.