Violation Detail
Standard Cited: 19100219 C02 I Mechanical power-transmission apparatus.
Inspection Nr: 1024668.015
Citation: 01005A
Citation Type: Serious
Abatement Date: 05/12/2015 2
Initial Penalty: $3,500.00
Current Penalty: $1,750.00
Issuance Date: 03/26/2015
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0111700
Contest Date:
Final Order: 04/13/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/13/2015 | $1,750.00 | 05/12/2015 | Serious | |
Penalty | Z: Issued | 03/26/2015 | $3,500.00 | 05/12/2015 | Serious |
Text For Citation: 01 Item/Group: 005A Hazard:
29 CFR 1910.219(c)(2)(i): The employer did not ensure all exposed parts of horizontal shafting seven (7) feet or less from floor or working platform, were protected by a stationary casing enclosing shafting completely or by a trough enclosing sides and top or sides and bottom of shafting as location requires. a. Location: Deburring Department - The horizontal shafts on the Baldor buffing machine were not guarded.