Violation Detail
Standard Cited: 19100179 D04 III Overhead and gantry cranes.
Inspection Nr: 997533.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,310.00
Current Penalty: $1,386.00
Issuance Date: 01/16/2015
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 02/11/2015
Gravity: 1
Report ID: 0524700
Contest Date:
Final Order: 02/11/2015
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/11/2015 | $1,386.00 | 02/11/2015 | Serious | |
Penalty | Z: Issued | 01/16/2015 | $2,310.00 | 02/11/2015 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.179(d)(4)(iii): Fixed ladder(s) on crane(s) were not constructed in compliance with 29 CFR 1910.27. P&W Painting Contractors, Inc. - Toledo, Ohio: On or about September 30, 2014, employees were exposed to trip/fall hazards in that the ladder rungs for the crane access platform were not uniformly spaced in accordance with 29 CFR 1910.27. The distance between rungs exceeded 12 inches in that the distance between the ground and the first rung was approximately 32 inches.