Violation Detail
Standard Cited: 19260859 G Mechanical demolition.
Inspection Nr: 1805913.015
Citation: 01005
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $16,550.00
Current Penalty: $11,585.00
Issuance Date: 04/16/2025
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity: 10
Report ID: 0111100
Contest Date:
Final Order: 05/12/2025
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/12/2025 | $11,585.00 | Serious | ||
Penalty | Z: Issued | 04/16/2025 | $16,550.00 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1926.859(g): During demolition, continuing inspections by a competent person were not made as the work progressed to detect hazards resulting from weakened or deteriorated floors, or walls, or loosened materials, and employees were also permitted to work where such hazards existed without being corrected by shoring, bracing, or other effective means: Canopy Structure - The employer did not ensure that during the demolition of an unbraced hotel canopy, a competent person conducted inspections.