Violation Detail
Standard Cited: 19100106 E06 II Flammable liquids.
Inspection Nr: 1647116.015
Citation: 01005
Citation Type: Serious
Abatement Date: 12/04/2024 2
Initial Penalty: $4,465.00
Current Penalty: $1,535.95
Issuance Date: 07/10/2023
Nr Instances: 4
Nr Exposed: 5
Related Event Code (REC):
Gravity: 5
Report ID: 0728500
Contest Date: 07/24/2023
Final Order: 01/21/2025
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/21/2025 | $1,535.95 | 12/04/2024 | Serious | |
Penalty | C: Contested | 07/25/2023 | $4,465.00 | 08/03/2023 | Serious | |
Penalty | Z: Issued | 07/10/2023 | $4,465.00 | 08/03/2023 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.106(e)(6)(ii): Grounding. Category 1 or 2 flammable liquids, or Category 3 flammable liquids with a flashpoint below 100 �F (37.8 �C), shall not be dispensed into containers unless the nozzle and container are electrically interconnected. Where the metallic floorplate on which the container stands while filling is electrically connected to the fill stem or where the fill stem is bonded to the container during filling operations by means of a bond wire, the provisions of this section shall be deemed to have been complied with. The employer failed to protect employees from potential fire hazards when Category 1 or 2 flammable liquids, or Category 3 flammable liquids with a flashpoint below 100 �F (37.8 �C), were being dispensed into containers without the nozzle and container being electrically interconnected as required. This was most recently demonstrated on or about January 31, 2023, when: a) The area surrounding an above-ground gasoline storage tank was not provided with appropriate grounding or bonding for a tank containing gasoline near the hurdle saw on the southeast wall. b) The area surrounding an above-ground gasoline storage tank was not provided with appropriate grounding or bonding for a tank containing gasoline near the hurdle saw on the northeast wall. c) The area surrounding an above-ground gasoline storage tank was not provided with appropriate grounding or bonding for a tank containing gasoline near the southeast wall mezzanine. d) The area surrounding an above-ground gasoline storage tank was not provided with appropriate grounding or bonding for a tank containing gasoline near the chipper/shaker. e) The area surrounding an above-ground gasoline storage tank was not provided with appropriate grounding or bonding for a tank containing diesel near the entrance across from the hurdle saw.