Violation Detail
Standard Cited: 19101025 E03 II Lead.
Inspection Nr: 1630595.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $14,063.00
Current Penalty: $11,954.00
Issuance Date: 04/07/2023
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 07/03/2023
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order: 05/01/2023
Related Event Code (REC):
Emphasis:
Substance: 1591
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/01/2023 | $11,954.00 | 07/03/2023 | Serious | |
| Penalty | Z: Issued | 04/07/2023 | $14,063.00 | 05/05/2023 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.1025(e)(3)(ii): The written compliance program for lead did not include the required sections: On or about October 12, 2022, the employer's written lead compliance program did not include the information required in sections [A] - [C] and [E] - [G]: a. The written lead compliance program did not describe each operation in which lead was emitted, as required under section [A]. b. The written lead compliance program did not have a description of the specific means that will be employed to achieve compliance, including engineering plans and studies used to determine methods selected for controlling exposure to lead, as required under section [B]. c. The written lead compliance program did not have a report of the technology considered in meeting the permissible exposure limit, as required under section [C]. d. The written lead compliance program did not have a detailed schedule for implementation of the program, including documentation such as copies of purchase orders for equipment, construction contracts, etc., as required under section [E]. e. The written lead compliance program did not have a work practice program which includes items required under paragraphs (g), (h) and (i) of this regulation, as required under section [F]. f. The written lead compliance program did not have an administrative control schedule required by paragraph (e)(5) of this section, if applicable, as required under section [G].
Translate