Violation Detail
Standard Cited: 19100303 B02 General.
Inspection Nr: 1536454.015
Citation: 01005
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $5,851.00
Current Penalty: $4,095.70
Issuance Date: 12/06/2021
Nr Instances: 1
Nr Exposed: 1
Abatement Date:
Gravity: 1
Report ID: 0316300
Contest Date:
Final Order: 12/28/2021
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/28/2021 | $4,095.70 | Serious | ||
Penalty | Z: Issued | 12/06/2021 | $5,851.00 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.303(b)(2): Listed or labeled electrical equipment was not used or installed in accordance with instructions included in the listing or labeling: On or about 06-14-2021, and times prior thereto, located at Federal Reserve Bank of Richmond, 701 E Byrd Street Richmond, Virginia 23219, located in room 229, employee(s) were exposed to electrical hazards from three electrical power strips/surge protectors that were "daisy-chained" and plugged directly into one another to provide power to computerized equipment. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employee(s) and their representatives were informed of this abatement.