Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1418803.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,856.00
Current Penalty: $3,856.00
Issuance Date: 01/24/2020
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 03/12/2020
Gravity: 5
Report ID: 0214500
Contest Date:
Final Order: 08/31/2020
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 01/24/2020 | $3,856.00 | 03/12/2020 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: a) Establishment: The employer did not develop detailed site specific procedural steps for shutting down equipment, including but not limited to, tablet machines, capsule machines (NJP 3500, NJP 2500 NJP 2000, NJP 1200), and the Sunmatch tumble blender, prior to maintenance/servicing, to prevent unexpected release of stored energy, thus exposing employees to an amputation hazard, on or about September 5, 2019.