Violation Detail
Standard Cited: 19100179 J03 Overhead and gantry cranes.
Inspection Nr: 1418637.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,577.00
Current Penalty: $5,303.90
Issuance Date: 10/07/2019
Nr Instances: 2
Nr Exposed: 150
Abatement Date: 11/05/2019
Gravity: 5
Report ID: 0636900
Contest Date:
Final Order: 10/10/2019
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/10/2019 | $5,303.90 | 11/05/2019 | Serious | |
Penalty | Z: Issued | 10/07/2019 | $7,577.00 | 11/05/2019 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.179(j)(3): Complete inspections of the crane was not being performed at intervals as generally defined in paragraph (j)(1)(ii)(b) of this section. On or about July 20, 2019, and times prior thereto, the employer failed to ensure the annual inspections were completed on the two Global 3-Ton overhead cranes located in the Battery Changing Department, exposing employees to dropping load or struck by hazards.