Violation Detail
Standard Cited: 19100119 J04 I Process safety management of highly hazardous chemicals.
Inspection Nr: 1297656.015
Citation: 01005
Citation Type: Other
Abatement Date: 09/13/2018 2
Initial Penalty: $0.00
Current Penalty: $3,000.00
Issuance Date: 08/24/2018
Nr Instances: 3
Nr Exposed: 5
Related Event Code (REC):
Gravity:
Report ID: 0625500
Contest Date:
Final Order: 09/18/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/18/2018 | $3,000.00 | 09/13/2018 | Other | |
Penalty | Z: Issued | 08/24/2018 | $0.00 | 09/13/2018 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.119(j)(4)(i): The employer did not perform inspection and tests on process equipment: On or about February 27, 2018, and at times prior thereto, the employer did not perform inspection and tests on process equipment to maintain its on-going mechanical integrity, specifically three (3) level control shutdown switches at the DCP Midstream Sonora Gas Plant.