Violation Detail
Standard Cited: 19100147 D06 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1279306.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,934.00
Current Penalty: $12,934.00
Issuance Date: 04/04/2018
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 10/01/2018
Gravity: 10
Report ID: 0626700
Contest Date: 04/30/2018
Final Order: 08/29/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/29/2018 | $12,934.00 | 10/01/2018 | Serious | |
Penalty | C: Contested | 06/11/2018 | $12,934.00 | 05/21/2018 | Serious | |
Penalty | Z: Issued | 04/04/2018 | $12,934.00 | 05/21/2018 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.147(d)(6): Prior to starting work on machines or equipment that have been locked out or tagged out, the employer did not ensure that the authorized employee verified that isolation and deenergization of the machine or equipment had been accomplished. On or about November 22, 2017, at the A&AT, LLC plant in La Porte, Texas, the employer failed to ensure employees followed energy control procedures to verify the Step 2 "C" Reactor isolation valve remained locked out/ tagged out and the isolation was validated prior to taking the blind off the piping connected to the reactor.