Violation Detail
Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1160674.015
Citation: 01005
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $6,663.00
Current Penalty: $3,332.00
Issuance Date: 09/07/2016
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 02/27/2017
Gravity:
Report ID: 0112000
Contest Date: 10/13/2016
Final Order: 03/17/2017
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/17/2017 | $3,332.00 | 02/27/2017 | Other | |
Penalty | C: Contested | 10/13/2016 | $6,663.00 | 10/25/2016 | Serious | |
Penalty | Z: Issued | 09/07/2016 | $6,663.00 | 10/25/2016 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.147(c)(4)(ii): The energy control procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy: Q1, Q Line Palletizer: On, or about, July 1, 2016, the Lock Out/Tag Out Procedure provided for the Chantland Palletizer/Pallet Magazine did not include the potential for gravity and/or mechanical hazards created when employees were required to access the lower elevator section by walking/standing on free-wheeling conveyor rollers.