Violation Detail
Standard Cited: 19260854 D Removal of walls, masonry sections, and chimneys.
Inspection Nr: 1147045.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $11,224.00
Current Penalty: $7,028.00
Issuance Date: 10/12/2016
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 10/24/2016
Gravity: 10
Report ID: 0215000
Contest Date: 06/26/2017
Final Order: 01/03/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/03/2018 | $7,028.00 | 10/24/2016 | Serious | |
Penalty | C: Contested | 06/26/2017 | $11,224.00 | 10/24/2016 | Serious | |
Penalty | Z: Issued | 10/12/2016 | $11,224.00 | 10/24/2016 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1926.854(d): Structural or load-supporting members on any floor were not cut or removed until all stories above such a floor have been demolished and removed. a) Jobsite, 2-story building: Employees utilized excavators with shear attachments to mechanically demolish a building from the sides. The roof, 2nd, and 1st stories are demolished simultaneously. Structural or load-supporting members on 2nd and 1st floor were not cut or removed until all stories above such floors have been demolished and removed. On or about 04/18/16.