Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1145409.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,017.00
Current Penalty: $5,785.00
Issuance Date: 11/04/2016
Nr Instances: 3
Nr Exposed: 6
Abatement Date: 11/25/2016
Gravity: 5
Report ID: 0213400
Contest Date:
Final Order: 12/02/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/02/2016 | $5,785.00 | 11/25/2016 | Serious | |
Penalty | Z: Issued | 11/04/2016 | $8,017.00 | 11/25/2016 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: a) Santec Inc./Linden, NJ- Production Area/Mixing Area: The employer failed to develop a written energy control procedure to be utilized during the cleaning of equipment such as but not limited to mixing tanks (#20, #30, and #40), the solids mixing tank and the ribbon blender. Condition observed on or about May 5, 2016.