Violation Detail
Standard Cited: 19261404 H07
Inspection Nr: 1142604.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,471.00
Current Penalty: $10,000.00
Issuance Date: 09/22/2016
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 11/01/2016
Gravity: 10
Report ID: 0418600
Contest Date:
Final Order: 10/12/2016
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/12/2016 | $10,000.00 | 11/01/2016 | Serious | |
Penalty | Z: Issued | 09/22/2016 | $12,471.00 | 09/30/2016 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1926.1404(h)(7): The boom sections, boom suspension systems (such as gantry A-frames and jib struts), and components were not rigged or supported to maintain stability upon the removal of the pins: a) On or about April 21, 2016 and times prior at a field near 4907 Marler Rd, Pike Road, Al: The employer failed to ensure blocking material was used to support and maintain stability of the lattice boom upon the removal of the lower pins between the tip section and center section.