Violation Detail
Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1014956.015
Citation: 01005
Citation Type: Other
Abatement Date: 04/05/2017 2
Initial Penalty: $5,000.00
Current Penalty: $1,500.00
Issuance Date: 06/15/2015
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): R
Gravity:
Report ID: 0317300
Contest Date: 07/01/2015
Final Order: 04/05/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/05/2017 | $1,500.00 | 04/05/2017 | Other | |
Penalty | C: Contested | 07/01/2015 | $5,000.00 | 07/02/2015 | Serious | |
Penalty | Z: Issued | 06/15/2015 | $5,000.00 | 07/02/2015 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.147(c)(6)(ii): The periodic inspection certification of energy control procedures did not contain the required documentation on identification of the machine or equipment, inspection date, employees included, and the person performing the inspection. a) Harbeson Plant, Maintenance Department - On or about 5/7/15, the employer failed to ensure periodic inspection certification of energy control procedures. The energy control book did not contain required documentation of inspection date, employees included and the person performing the inspection for the skinner machine and other equipment. Note: Pursuant to 29 CFR 1903.19, the employer must submit abatement certification, required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.