Violation Detail
Standard Cited: 19260062 F02 I Lead
This violation item has been deleted.
Inspection Nr: 1719781.015
Citation: 01004C
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/24/2024
Nr Instances: 4
Nr Exposed: 10
Abatement Date: 06/11/2024
Gravity: 10
Report ID: 0112000
Contest Date: 05/07/2024
Final Order: 09/20/2024
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/20/2024 | $0.00 | 06/11/2024 | Serious | |
Penalty | C: Contested | 05/10/2024 | $0.00 | 06/11/2024 | Serious | |
Penalty | Z: Issued | 04/24/2024 | $0.00 | 06/11/2024 | Serious |
Text For Citation: 01 Item/Group: 004C Hazard:
29 CFR 1926.62(f)(2)(i): The employer did not implement a respiratory protection program in accordance with 29 CFR 1910.134(b) through (d) (except (d)(1)(iii)), and (f) through (m) for each employee required by 29 CFR 1926.62 to use a respirator: Decommissioned Millstone Power Station Unit No. 1 Roof: On or about October 24, 2023, and sometime thereafter, the employer did not implement a respiratory protection program in accordance with 29 CFR 1910.134(b) through (d) (except (d)(1)(iii)), and (f) through (m) for each employee required by 29 CFR 1926.62 to use a respirator while engaging in torch cutting and power cutting operations on lead-painted surfaces and steel structures within the following rooftop Millstone Power Station Unit 1 locations: a) Maintenance Shop Roof b) Turbine Building Roof c) Reactor Building Roof d) Yard - Radwaste & Radwaste Storage Roof