Violation Detail
Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1793646.015
Citation: 01004B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/19/2025
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 06/30/2025
Gravity: 5
Report ID: 0336000
Contest Date:
Final Order: 06/13/2025
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/13/2025 | $0.00 | 06/30/2025 | Serious | |
Penalty | Z: Issued | 05/19/2025 | $0.00 | 06/13/2025 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1910.147(c)(6)(ii): The periodic inspection certification of energy control procedures did not contain the required documentation on identification of the machine or equipment, inspection date, employees included, and the person performing the inspection. a.) Viking Tool & Gage, Inc. 11210 State Highway 18 Conneaut Lake, PA 16316: on or about 12-05-2024, and times prior thereto: Employees perform servicing and maintenance on equipment including, but not limited to, the Bliss 60-ton press machine #PN21 in the Stamping Area without periodic inspections of energy control procedures occurring or being certified. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.