Violation Detail
Standard Cited: 19100107 B08 Spray finishing using flammable and combustible materials.
Inspection Nr: 1784023.015
Citation: 01004B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/07/2025
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 02/10/2025
Gravity: 1
Report ID: 0728900
Contest Date:
Final Order: 01/28/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/28/2025 | $0.00 | 02/10/2025 | Serious | |
Penalty | Z: Issued | 01/07/2025 | $0.00 | 01/13/2025 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1910.107(b)(8):Each spray booths was not separated from other operations by not less than 3 feet, or by a greater distance, or by such partition or wall as to reduce the danger from juxtaposition of hazardous operations. Employees were exposed to fire and combustion hazards. This was most recently documented on or about October 24, 2024 at 7050 North 97th Circle Plaza, Omaha, Nebraska. Spray booths in the finishing area were not separated from sanding operations by at least 3 feet.