Violation Detail
Standard Cited: 19100269 D02 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1781684.015
Citation: 01004B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $3,750.00
Issuance Date: 11/22/2024
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 06/02/2025
Gravity: 5
Report ID: 0521100
Contest Date: 12/19/2024
Final Order: 04/14/2025
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/14/2025 | $3,750.00 | 06/02/2025 | Other | |
Penalty | C: Contested | 01/15/2025 | $0.00 | 12/23/2024 | Serious | |
Penalty | Z: Issued | 11/22/2024 | $0.00 | 12/23/2024 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1910.269(d)(2)(iii): Procedures shall be developed, documented, and used for the control of potentially hazardous energy covered by paragraph (d) of this section: On or about August 26, 2024; at a facility located at 1101 Mill Street in Niagara, WI; employees conducted an annual shutdown of the generators and turbines and isolated the river from the hydroelectric power generation system; however, the employer had not developed an energy control procedure for locking out hydroelectric power generation equipment and for isolation of the river from the system.