Violation Detail
Standard Cited: 19100107 D02 Spray finishing using flammable and combustible materials.
Inspection Nr: 1754026.015
Citation: 01004B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/23/2024
Nr Instances: 1
Nr Exposed: 20
Abatement Date: 12/20/2024
Gravity: 5
Report ID: 1032500
Contest Date:
Final Order: 11/19/2024
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/19/2024 | $0.00 | 12/20/2024 | Serious | |
Penalty | Z: Issued | 10/23/2024 | $0.00 | 11/19/2024 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1910.107(d)(2): Mechanical ventilation was not kept in operation at all times while spraying operations were being conducted and for a sufficient time thereafter to allow vapors from drying coated articles and drying finishing material residue to be exhausted: a) On and at times prior to June 10th, 2024, vapors were not exhausted during painting operations. Employees paint parts of transformers as well as the main transformer housing unit daily.