Violation Detail
Standard Cited: 19100217 E01 II A Mechanical power presses.
Inspection Nr: 1728691.015
Citation: 01004B
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/21/2024
Nr Instances: 1
Nr Exposed: 1
Abatement Date:
Gravity: 5
Report ID: 0419700
Contest Date:
Final Order: 04/15/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/15/2024 | $0.00 | Serious | ||
| Penalty | Z: Issued | 03/21/2024 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1910.217(e)(1)(ii)(A): Inspections and tests of each press on a weekly basis were not being completed to determine the condition of the clutch/ brake mechanism, anti-repeat feature and single stroke mechanism. a. On or about February 15, 2024; in the CNC area, employees were operating a 12-ton mechanical power press without the employer having inspected, tested and documented the condition of the clutch/brake mechanism, anti-repeat feature on a weekly basis as required by the standard., exposing employees to amputation hazards.